Electricidade de Moçambique
Reinforcement and Expansion of EDM's National Transmission Network
Introduction
In 2015 EDM began work on the implementation of the significant project for "Reinforcement and Expansion of the National Transportation Network of EDM", comprising 4 packages: The main package and optional packages 1, 2 and 3.
Tecnel Service is the main subcontractor of the Consortium responsible for the Main Package, performing the following works: Assembly of the Substations comprising of all structures and equipment of High and Low Voltage, including Land Network and Control Equipment.


Of 2015 to 2016
-
Assembly of structures and equipment comprising of High and Low Voltage, including Land Network and Control Equipment in the new Substations of Massinga and Macia and also in the existing Substations of Maxixe and Lindela.

Other Work Performed
2016
-
Continuation of works initiated in 2015
-
Start of works at the new Lindela Substation
2015
-
Beginning of works on the new Macia Substation 275/110 kV - 250 MVA
-
Works begins on the new Massinga Substation 110/33kV - 30 MVA
-
Beginning of the works at the Maxixe Substation